Specification library

Draft clauses for specifiers and quantity surveyors covering barriers, gates, rising bollards, road blockers, access control, intercoms and maintenance. Complete the project blanks and check each clause before use, alongside the Compliance page.

How to use these clauses

  • Paste the short or full clause into the project specification. Every square-bracket item, such as [width], is a blank; fill it for the project and delete unused options, such as [included / by others].
  • For items 1 to 8, choose one product ending and delete the other. Ending A is for a private client choosing a named product; check the procurement requirements before using ending B in a public tender.
  • Where the Procurement Act 2023 applies, follow section 56(4) to (6) for equivalent standards and section 56(7) to (8) for named products, which may be named only where necessary to explain the requirements and with equivalent quality or performance not disadvantaged. Adding "or equivalent" does not by itself make a specification compliant.
  • Named brands are examples of preferred brands chosen from experience. They are not evidence of a manufacturer relationship.
  • Use classifications only for the stated system, product, activity or information scope. CAWS titles are historical work sections; NRM1 mappings are from NBS and NRM2 is for the project QS to confirm.
  • Check that the cited standards are current at the date of tender. Where a clause says "current edition", use the edition current at the tender date unless the contract says otherwise.

Eleven clauses

Choose a short or full clause, complete its blanks and check the stated classification scope. Items 1 to 8 also have two alternative product endings.

Rising arm barrier

Draft: to be checked by UrbanForte before use.

Uniclass system
Ss_25_36_95_70 Rising arm barrier systems
Uniclass product
Pr_30_59_59_72 Rising arm vehicular barriers
CAWS work section
Q41 Barriers/guardrails (CAWS work section, historical title)
NRM1
8.4.4 Barriers and guardrails (mapping from the NBS Uniclass Systems table v1.44; not checked against the RICS publication)
NRM2
Project QS to confirm.
CPV, supply
34926000-4 Car park control equipment (for car-park entry/exit control)
CPV, installation
51100000-3 Installation services of electrical and mechanical equipment (for a separately procured equipment-installation service); 45233280-5 Erection of road-barriers (only where the work genuinely matches road-barrier works)
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment)
Short clause
Supply, install, test and commission [number] automatic rising arm barrier(s) at [location], complete with drive unit, arm, controls, safety devices, signage and accessories. Work included: [list]. Work by others: [list]. Select safety devices from the site risk assessment and provide [separate pedestrian route / guarding / signage] as specified in the full clause. Test controls, interfaces, safety devices, power-failure operation and manual release, with force testing where required. Provide the clause 11 handover pack, with the technical file retained by the installer acting as manufacturer. Train [number] client nominees and record attendance.
Full clause
1.1 Scope

Supply, install, test and commission [number] automatic rising arm barrier(s) at [location], complete with drive unit, arm, controls, safety devices, signage and all accessories needed for a safe, working installation.

Work included: [list]. Work by others: [list].

1.2 Description

- Barrier type: automatic rising arm barrier, [left / right]-hand as viewed from [direction].
- Clear opening to be controlled: [width] m.
- Arm: [type, e.g. straight / articulated / folding], length [length] m, material [material], [with / without] arm lights, [with / without] skirt or lower guard, [with / without] arm rest at the free end.
- Cabinet / housing: [material], [finish], [colour].
- Duty: suitable for [description of use, e.g. car park entry / site entrance] with [number] operating cycles per [hour / day].
- Arm breakaway or release: [required / not required].
- Manual release for use during power failure: [type], operable by persons permitted by the client only.

1.3 Performance requirements

- Opening time: [time] seconds. Closing time: [time] seconds.
- Operating cycles: rated for at least [number] cycles per [period] without overheating.
- Wind: arm to remain stable and operable in wind speeds up to [speed] at the site location.
- Operating temperature range: [range] °C.
- Ingress protection of housing and electrical components: [IP rating].
- Power failure behaviour: [fail open / fail closed / stay in last position], with [battery back-up for number of cycles / no battery back-up].
- The equipment must be designed, installed and commissioned so that the risks of impact, crushing, shearing, drawing-in and lifting are reduced to an acceptable level, as shown by the risk assessment and force testing.

1.4 Standards and legislation

Comply with the current editions of the following, as relevant:

- Supply of Machinery (Safety) Regulations 2008 (as amended). The completed powered installation is machinery. The installer who completes it and acts as manufacturer must meet the manufacturer's duties, compile and retain the technical file for the enforcing authorities, and provide the client with the declaration of conformity and user and maintenance instructions in English. Apply UKCA or CE marking under the applicable Great Britain conformity route. SI 2026 No. 867 comes into force on 20 January 2027: Part 2 amends the Great Britain regime, including recognition of specified compliance routes under Regulation (EU) 2023/1230; Part 3 provides Northern Ireland enforcement and revokes the 2008 Regulations for Northern Ireland only, subject to transitional provisions. Check the regime applicable at the date and place of supply or first putting into service.
- BS EN 12453:2017+A1:2021 Industrial, commercial and garage doors and gates. Safety in use of power operated doors. Requirements and test methods.
- BS EN 12604 Industrial, commercial and garage doors and gates. Mechanical aspects. Requirements and test methods.
- BS EN 13241 Industrial, commercial, garage doors and gates. Product standard, performance characteristics.
- BS EN 12978, current edition: Industrial, commercial and garage doors and gates and pedestrian doorsets. Protective devices for power operated doors and gates. Requirements and test methods (for safety devices supplied as separate components).
- DHF TS 013-1:2025 Code of practice for the safety of industrial doors, domestic garage doors, powered gates and traffic barriers. Part 1: On-site guide (supersedes the 2021 edition).
- Workplace (Health, Safety and Welfare) Regulations 1992, where the barrier is in or serves a workplace.
- BS 7671 Requirements for Electrical Installations (IET Wiring Regulations, 18th Edition, current amendment) and the Electricity at Work Regulations 1989.
- Gate Safe guidance on the safe design, installation and maintenance of automated gates and barriers.
- Manufacturer's installation and maintenance instructions.

1.5 Safety devices and force testing

- Provide safety devices chosen from the risk assessment. As a minimum, consider: [photocells at height(s) and positions], [presence detection loops], [safety edge on arm], [arm lights], [warning light / beacon], [warning signs].
- Vehicle safety loop(s) or other presence detection to prevent the arm closing onto a vehicle: [required: number and position].
- Pedestrian route: the barrier must not be the means of pedestrian access. Provide [separate pedestrian route / guarding / signage] to discourage people walking through the barrier opening.
- Where the closing arm can impact a person, measure forces at the test points set out in BS EN 12453 using a calibrated force testing instrument. Forces must be within the limits in BS EN 12453. Record results on the commissioning record.
- Safety devices to be monitored (self-checked) where the risk assessment or BS EN 12453 requires it.
- Fully automatic or remote operation, where the user cannot see the barrier, only where the risk assessment shows the level of protection is adequate for that mode.

1.6 Controls and integration

- Control method(s): [access control reader / ANPR / intercom / push button / key switch / remote / timer / ticket system / other].
- Open command from: [list systems, e.g. Paxton Net2 access control: see clause 7; GSM intercom: see clause 8]. The named brand is for example only, as a preferred brand chosen from experience.
- Free exit: [exit loop / exit reader / push button / none].
- Fire alarm interface: [arm to open / stay closed / none] on fire alarm signal, as agreed with the [fire strategy / client].
- Other interfaces: [car park management / CCTV / BMS / other].
- Control panel location: [integral / remote at location].
- All interfaces must be wired so that no external input can override or bypass the safety devices.

1.7 Electrical (BS 7671)

- Power supply: [voltage] supply to [location], [by Contractor / by others], terminating in a local lockable isolator within [distance] of the equipment.
- Protection: [RCD / RCBO type and rating], as required by BS 7671 and the manufacturer.
- Earthing and bonding to BS 7671.
- Cable routes and ducts: [by Contractor / by others], size [size] mm, with draw cords, from [location] to [location].
- Low-voltage and data cables to be in separate ducts from mains cables.
- Provide an Electrical Installation Certificate (or Minor Electrical Installation Works Certificate where suitable) to BS 7671 for the power supply work done by the Contractor.

1.8 Groundworks and foundations: [included / by others]

- Foundation: [size] to the manufacturer's details and [structural engineer's design, where required].
- Ducts, draw pits and loop slots: [included / by others].
- Surface reinstatement: [included / by others], to match [existing surface].
- Where by others: the Contractor must provide foundation and duct drawings to the groundworks contractor by [date / stage] and inspect the foundation before installation.

1.9 Finishes

- Housing finish: [polyester powder coat / galvanised / stainless steel / manufacturer's standard], colour [RAL or BS colour].
- Arm: [colour], with [red and white reflective banding / other markings].
- Signage: [warning and instruction signs] to suit the risk assessment.

1.10 Testing and commissioning

- Test and commission to the manufacturer's instructions, BS EN 12453 and DHF TS 013-1:2025.
- Carry out and record: function tests of every control and interface; tests of every safety device; force tests where required; power-failure and manual-release tests; electrical tests to BS 7671.
- Give the client [number] working days' notice of commissioning so they can attend.
- Do not hand over until all tests are passed and recorded.

1.11 Documentation and handover

Provide the handover pack described in clause 11, including the declaration of conformity, UKCA or CE marking evidence under the applicable regime, risk assessment, commissioning and force test records, and user and maintenance instructions in English. The installer acting as manufacturer must compile and retain the technical file for the enforcing authorities; it is not a client handover document.

1.12 Training

Train [number] client nominees in safe daily use, manual release, what to do in a fault, and the owner's duties. Record attendance.

1.13 Warranty

- Parts: [term] from the date of handover.
- Labour: [term] from the date of handover.
- Conditions: [e.g. warranty depends on planned maintenance being carried out by a competent person at the stated intervals; excludes vehicle impact, vandalism and misuse].

1.14 Maintenance

- Planned maintenance: [included for term / quoted separately], see clause 9.
- Reactive maintenance: [included for term / quoted separately], see clause 10.

1.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and model, e.g. Ditec model], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and model] or equivalent. Any equivalent must meet every requirement in this clause. Evidence of equivalence to be provided with the tender.

Swing gate

Draft: to be checked by UrbanForte before use.

Uniclass system
Ss_25_32_35_37 Hinged gate systems
Uniclass product
Pr_30_59_34_14 Carbon steel gates (use for carbon steel gates only)
CAWS work section
Q40 Fencing (CAWS work section, historical title)
NRM1
8.4.1 Fencing and railings (mapping from the NBS Uniclass Systems table v1.44; not checked against the RICS publication)
NRM2
Project QS to confirm.
CPV, supply
44221310-1 Access gates; 44221300-8 Gates (broader alternative)
CPV, installation
45421148-3 Installation of gates
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment)
Short clause
Supply, install, test and commission [single leaf / pair of] automated swing gate(s) at [location], complete with leaves, posts, hinges, drives, controls, safety devices, stops and locks. Work included: [list]. Work by others: [list]. Existing gate to be automated: [yes / no]. Check existing gates, hinges and posts before automation. Control crushing, shearing, impact and trapping risks through the risk assessment, safety devices and force testing. Provide a [separate pedestrian gate / route]. Record commissioning tests and provide the clause 11 handover pack. Warranty: parts [term], labour [term], conditions [conditions].
Full clause
2.1 Scope

Supply, install, test and commission [single leaf / pair of] automated swing gate(s) at [location], complete with gate leaves, posts, hinges, drives, controls, safety devices, stops, locks and all accessories needed for a safe, working installation.

Work included: [list]. Work by others: [list]. Existing gate to be automated: [yes / no]: if yes, see 2.3.

2.2 Description

- Clear opening: [width] m. Gate height: [height] m.
- Leaf construction: [material], infill [type, e.g. vertical bar / mesh / solid board], [finish].
- Direction of opening: [inward / outward], viewed from [direction].
- Ground: [level / sloping: gradient]. Gates opening over rising ground not acceptable unless the design deals with it.
- Drive: [underground / above-ground ram / articulated arm], [electromechanical / hydraulic].
- Posts / pillars: [new steel posts / existing pillars: condition to be checked].
- Hinges: [type], suitable for the leaf weight and wind load.
- Gate stops: positive mechanical stops in the open and closed positions.
- Locking: [electromagnetic lock / drop bolt / motor lock / none].
- Manual release for use during power failure: [type], operable by persons permitted by the client only.

2.3 Performance requirements

- Leaf weight: up to [weight] kg per leaf. Leaf width: up to [width] m.
- Opening time: [time] seconds. Opening angle: [angle] degrees.
- Operating cycles: rated for at least [number] cycles per [period].
- Wind: gate and drive to withstand and operate in wind speeds up to [speed] at the site location, taking account of the infill.
- Operating temperature range: [range] °C. Ingress protection: [IP rating].
- Power failure behaviour: [fail open / fail locked / stay in last position], with [battery back-up for number of cycles / no battery back-up].
- Where an existing gate is automated, the Contractor must check its condition, hinges and posts before work starts and report any work needed. Automating an existing gate creates new machinery under the Supply of Machinery (Safety) Regulations 2008, and the full requirements of this clause apply.
- Crushing, shearing, impact and drawing-in hazards, including at the hinge side and between the leaf and fixed objects, to be removed or controlled as shown by the risk assessment and force testing.

2.4 Standards and legislation

As clause 1.4. In addition, comply with Gate Safe guidance on gaps at the hinge side and between leaves, and on gates near public footways.

2.5 Safety devices and force testing

- Provide safety devices chosen from the risk assessment. As a minimum, consider: [photocells: number, height and positions on both sides], [safety edges on leading and trailing edges], [presence detection], [warning light / beacon], [warning signs].
- Hinge-side and trapping gaps: keep safety distances to BS EN 12453 or fit guards.
- Where a leaf opens towards a wall, fence or other fixed object, control the trapping zone with [safety distance / safety edge / guarding].
- Measure forces at the test points set out in BS EN 12453, using a calibrated force testing instrument, at the closing and opening edges where people could be struck or crushed. Forces must be within the limits in BS EN 12453. Record results.
- Safety devices to be monitored where the risk assessment or BS EN 12453 requires it.
- Fully automatic or remote operation, where the user cannot see the gate, only where the risk assessment shows adequate protection.
- Pedestrian use: provide a [separate pedestrian gate / route]. Where people may still use the vehicle opening, the safety measures must allow for this.

2.6 Controls and integration

As clause 1.6, with: open command from [list]; free exit by [loop / reader / button / none]; fire and emergency services access by [key switch / code / fire alarm interface / other], as agreed with [the client / fire strategy]; auto-close [required after time delay / not required].

2.7 Electrical (BS 7671)

As clause 1.7.

2.8 Groundworks and foundations: [included / by others]

- Post foundations: [size] to the manufacturer's details and [structural engineer's design, where required].
- Underground drive foundation boxes: drained to [drainage connection / soakaway], [included / by others].
- Ducts and draw pits: [included / by others], sizes [size] mm.
- Surface reinstatement: [included / by others].
- Where by others: provide drawings by [date / stage] and inspect before installation.

2.9 Finishes

- Gate and posts: [hot-dip galvanised / polyester powder coat over galvanising / other], colour [RAL or BS colour].
- Fixings: [stainless steel / galvanised], tamper-resistant where reachable by the public.
- Signage: [warning and instruction signs].

2.10 Testing and commissioning

As clause 1.10, including checks that mechanical stops are effective and that the leaves cannot leave their hinges under any foreseeable load.

2.11 Documentation and handover

As clause 1.11. See clause 11.

2.12 Training

As clause 1.12.

2.13 Warranty

As clause 1.13: parts [term], labour [term], conditions [conditions].

2.14 Maintenance

As clause 1.14.

2.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and model, e.g. Came drive model], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and model] or equivalent. Any equivalent must meet every requirement in this clause. Evidence of equivalence to be provided with the tender.

Sliding gate

Draft: to be checked by UrbanForte before use.

Uniclass system
Ss_25_32_35_80 Sliding gate systems
Uniclass product
Pr_30_59_59_79 Sliding vehicular barriers (use only where this describes the product); Pr_30_59_34_14 Carbon steel gates (alternative for carbon steel gates)
CAWS work section
Not shown.
NRM1
8.4.1 Fencing and railings (mapping from the NBS Uniclass Systems table v1.44; not checked against the RICS publication)
NRM2
Project QS to confirm.
CPV, supply
44221310-1 Access gates; 44221300-8 Gates (broader alternative)
CPV, installation
45421148-3 Installation of gates
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment)
Short clause
Supply, install, test and commission [number] automated sliding gate(s) at [location], complete with leaf, track or cantilever frame, posts, guides, drive, controls and safety devices. Type: [tracked / cantilever]. Existing gate to be automated: [yes / no]. Provide positive mechanical end stops, anti-derailment and anti-fall retention. Guard drawing-in and shearing points and control trapping risks identified by the risk assessment. Carry out force testing as clause 2.5. Test that the gate cannot pass the end stops or leave the track, record the results and provide the clause 11 handover pack.
Full clause
3.1 Scope

Supply, install, test and commission [number] automated sliding gate(s) at [location], complete with gate leaf, track or cantilever frame, posts, guides, drive, controls, safety devices, stops and all accessories needed for a safe, working installation.

Work included: [list]. Work by others: [list]. Existing gate to be automated: [yes / no].

3.2 Description

- Type: [tracked / cantilever].
- Clear opening: [width] m. Gate height: [height] m. Run-back space available: [length] m on the [left / right].
- Construction: [material], infill [type], [finish].
- Drive: [electromechanical, rack and pinion / other], position [location].
- Guide and catch posts: [type].
- Mechanical travel stops: positive end stops at both ends of travel, independent of the drive and limit switches, that cannot fail under any foreseeable load.
- Anti-derailment and anti-fall: the gate must be retained so that it cannot leave its track or guides, or fall over, under any foreseeable load, including if a roller or guide fails.
- Locking: [type / none]. Manual release: [type], operable by persons permitted by the client only.

3.3 Performance requirements

- Gate weight: up to [weight] kg. Opening speed: [speed] m/s, or opening time [time] seconds.
- Operating cycles: rated for at least [number] cycles per [period].
- Wind: as clause 2.3.
- Operating temperature range: [range] °C. Ingress protection: [IP rating].
- Power failure behaviour: [fail open / fail locked / stay in last position], with [battery back-up for number of cycles / no battery back-up].
- Existing gates: as clause 2.3.
- Crushing at the closing edge and catch post, shearing and drawing-in at the run-back and between gate and fixed parts, and trapping in the infill to be removed or controlled as shown by the risk assessment and force testing.

3.4 Standards and legislation

As clause 1.4. Note DHF and HSE warnings on sliding gates leaving their tracks: travel stops and anti-fall retention are critical safety items.

3.5 Safety devices and force testing

- Provide safety devices chosen from the risk assessment. As a minimum, consider: [photocells: number, heights and positions], [safety edges on leading edge, trailing edge and catch post], [guarding or mesh to the run-back area and drive], [warning light / beacon], [warning signs].
- Drawing-in and shearing points at rollers, pinion and guides to be guarded.
- Infill: openings in the gate and adjacent fence in the run-back zone must not allow hands or fingers to be drawn in, or must be guarded.
- Force testing: as clause 2.5, at the closing edge and at any other point identified by the risk assessment.
- Monitored safety devices, automatic and remote operation, pedestrian use: as clause 2.5.

3.6 Controls and integration

As clause 2.6.

3.7 Electrical (BS 7671)

As clause 1.7.

3.8 Groundworks and foundations: [included / by others]

- Track beam or cantilever foundation: [size], level to [tolerance], to the manufacturer's details and [structural engineer's design, where required].
- Drive foundation: [size].
- Ducts and draw pits: [included / by others].
- Drainage of the track (tracked gates): [required / not required].
- Surface reinstatement: [included / by others].
- Where by others: provide drawings by [date / stage] and inspect before installation.

3.9 Finishes

As clause 2.9.

3.10 Testing and commissioning

As clause 1.10. Include a test that the gate cannot pass the end stops or leave the track when driven or pushed, and record it.

3.11 Documentation and handover

As clause 1.11. See clause 11.

3.12 Training

As clause 1.12.

3.13 Warranty

As clause 1.13: parts [term], labour [term], conditions [conditions].

3.14 Maintenance

As clause 1.14.

3.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and model, e.g. Came drive model], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and model] or equivalent. Any equivalent must meet every requirement in this clause. Evidence of equivalence to be provided with the tender.

Manual barrier

Draft: to be checked by UrbanForte before use.

Uniclass system
Not shown.
Uniclass product
Pr_30_59_59_39 Horizontal swing vehicular barriers (use for horizontal swing vehicular barriers); Pr_30_59_59_72 Rising arm vehicular barriers (use for manual rising arm vehicular barriers)
CAWS work section
Not shown.
NRM1
Not shown.
NRM2
Project QS to confirm.
CPV, supply
34926000-4 Car park control equipment (for a manual car-park access barrier)
CPV, installation
51120000-9 Installation services of mechanical equipment (for equipment-only installation); 45421148-3 Installation of gates (where the actual item is an access gate); 45233280-5 Erection of road-barriers (only where the work genuinely matches road-barrier works)
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment)
Short clause
Supply and install [number] manually operated [swing-arm / rising-arm] barrier(s) at [location], complete with posts, arm, rest or receiver post, locking and fixings. Clear opening: [width] m. Provide secure hold-open arrangements, control pinch and shear points, and check that the arm cannot fall or swing onto people or vehicles. Finish and foundations are as specified in the full clause. Check operation, locking and counterbalance, and record results. Provide product data, installation record, user and maintenance instructions, keys [number of sets] and the asset reference. Brief [number] client nominees on safe use.
Full clause
4.1 Scope

Supply and install [number] manually operated [swing-arm / rising-arm] barrier(s) at [location], complete with posts, arm, rest or receiver post, locking and all fixings.

4.2 Description

- Type: [swing-arm / manual rising-arm (counterbalanced)].
- Clear opening: [width] m. Arm height when closed: [height] mm.
- Arm: [material, section], [single / double], [with / without] drop leg.
- Receiver / rest post: [type], with [padlock / integral lock].
- Locking in open and closed positions: [padlock / integral lock / key type].
- Counterbalance (rising arm): [type], so the arm stays where put and cannot drop.

4.3 Performance requirements

- Operating force: arm to be operable by one person with a force not exceeding [force] N. [Remove or fill in: check against BS EN 12604.]
- Arm to be held securely open so it cannot swing or fall closed in wind up to [speed] or if knocked.
- Pinch and shear points at the pivot and receiver to be removed or guarded.
- Durability: suitable for [number] operations per [period].

4.4 Standards and legislation

- BS EN 12604 (mechanical aspects), as relevant to manual barriers.
- Workplace (Health, Safety and Welfare) Regulations 1992, where in or serving a workplace.
- DHF TS 013-1:2025 (section on manual doors and gates).
- Manufacturer's instructions.
- A manual barrier is not powered machinery; the Supply of Machinery (Safety) Regulations 2008 apply only if it is later powered.

4.5 Safety devices and force testing

- Powered force testing: not applicable.
- Provide [hold-open catch / lock], [high-visibility banding], [reflective markers] and [signs] to suit the risk assessment.
- Check that the arm cannot fall or swing onto a person or vehicle when released.

4.6 Controls and integration

Not applicable unless [padlock / key system / key safe] integration is required: [details].

4.7 Electrical (BS 7671)

Not applicable. If arm lights or other powered items are added: [details], to BS 7671.

4.8 Groundworks and foundations: [included / by others]

- Post foundations: [size] to the manufacturer's details, or [bolt-down base plates on existing surface: check suitability].
- Surface reinstatement: [included / by others].

4.9 Finishes

- [Hot-dip galvanised / polyester powder coat over galvanising], colour [RAL or BS colour], with [red and white reflective banding].

4.10 Testing and commissioning

Check smooth operation, locking in both positions, hold-open, counterbalance and absence of pinch points. Record results.

4.11 Documentation and handover

Provide: product data, installation record, user and maintenance instructions, keys [number of sets], and the asset reference. See clause 11.

4.12 Training

Brief [number] client nominees on safe use and locking.

4.13 Warranty

Parts: [term]. Labour: [term]. Conditions: [conditions].

4.14 Maintenance

Inspection and lubrication at [frequency]: [included / quoted separately]. See clause 9.

4.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and model], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and model] or equivalent. Any equivalent must meet every requirement in this clause. Evidence of equivalence to be provided with the tender.

Rising bollards

Draft: to be checked by UrbanForte before use.

Uniclass system
Ss_25_36_95_72 Rising bollard systems
Uniclass product
Pr_20_76_08_12 Carbon steel rising bollards; Pr_20_76_08_84 Stainless steel rising bollards
CAWS work section
Q50 Site/street furniture/equipment (CAWS work section, historical title)
NRM1
8.4.4 Barriers and guardrails (mapping from the NBS Uniclass Systems table v1.44; not checked against the RICS publication)
NRM2
Project QS to confirm.
CPV, supply
34928450-7 Bollards (describe rising operation and material in the clause)
CPV, installation
45233291-5 Installation of bollards
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment)
Short clause
Supply, install, test and commission [number] automatic rising bollard(s) at [location], complete with foundation cassettes, drives, controls, safety devices, drainage, signage and accessories. Static bollards to complete the line: [number / none]. Select safety devices from the risk assessment and provide presence detection to prevent a bollard rising beneath a vehicle, cyclist or pedestrian. Where impact rated, match the installed foundation to the tested arrangement and provide rating evidence. Record commissioning, emergency-operation and manual-lowering tests. Provide the clause 11 handover pack and training, including manual lowering and emergency operation.
Full clause
5.1 Scope

Supply, install, test and commission [number] automatic rising bollard(s) at [location], complete with bollard units, foundation cassettes, drive units, controls, safety devices, drainage connections, signage and all accessories needed for a safe, working installation. Static bollards to complete the line: [number / none].

5.2 Description

- Bollard type: [electromechanical / hydraulic / pneumatic], [automatic / semi-automatic].
- Height above finished ground when raised: [height] mm. Diameter: [diameter] mm.
- Material: [steel / stainless steel], [finish].
- Spacing between bollards (clear gap): [gap] mm.
- Head: [with / without] LED crown lights. Reflective banding: [required / not required].
- Manual lowering for power failure: [type], operable by persons permitted by the client only.

5.3 Performance requirements

- Rise time: [time] seconds. Lower time: [time] seconds.
- Operating cycles: rated for at least [number] cycles per [period].
- Impact rating: [not required / required: rating, standard and test vehicle as below].
- Where an impact rating is required, state the rating in the format of the chosen standard: [rating], tested to [BS ISO 22343-1:2023 / PAS 68 (legacy test, product accepted) / IWA 14-1 (legacy test, product accepted) / PAS 170-1:2017 low-speed trolley test for single bollards].
- The installed foundation must match the foundation used in the impact test. Any change needs the manufacturer's written confirmation that the rating is kept.
- Load when lowered: [load class or axle load] for vehicles passing over.
- Operating temperature range: [range] °C. Ingress protection: [IP rating].
- Power failure behaviour: [stay up / lower / stay in last position], with [battery back-up / emergency lowering].
- Emergency fast operation: [required / not required].

5.4 Standards and legislation

As clause 1.4, as relevant to powered bollards. In addition, where an impact rating is required:

- BS ISO 22343-1:2023 Security and resilience. Vehicle security barriers. Part 1: Performance requirement, vehicle impact test method and performance rating (replaces IWA 14-1:2013 and supersedes PAS 68:2013).
- BS ISO 22343-2:2023 Security and resilience. Vehicle security barriers. Part 2: Application (guidance on selection, installation and use; replaces IWA 14-2 and PAS 69).
- PAS 170-1:2017 Vehicle security barriers. Low speed impact testing. Part 1: Trolley impact test method for bollards: for low-speed trolley testing of single bollards; not equivalent to a full-scale vehicle impact test.
- NPSA guidance on hostile vehicle mitigation, current edition, where relevant.

5.5 Safety devices and force testing

- Provide safety devices chosen from the risk assessment. As a minimum, consider: [presence detection loops], [photocells], [traffic lights: red / green], [warning light on bollard head], [audible warning], [warning and instruction signs], [road markings].
- A bollard must not rise under a vehicle, cyclist or pedestrian. Provide presence detection to prevent this.
- Lifting hazard: control the risk of a bollard lifting a person or vehicle by [detection / rising force limits / other], as shown by the risk assessment.
- Force testing: where the risk assessment shows that a person can be struck or lifted by the rising bollard, test and record forces as required by BS EN 12453 and DHF TS 013-1:2025. [UrbanForte to confirm wording: see questions.]
- Monitored safety devices: where required by the risk assessment.

5.6 Controls and integration

As clause 1.6, with: traffic signal control [required / not required]; emergency services access by [key switch / code / other]; [security control room / guard house] interface by [details]; emergency fast operation trigger by [details].

5.7 Electrical (BS 7671)

As clause 1.7. Hydraulic power units and control panels located at [location], [distance] from the bollards, with ducts sized [size] mm.

5.8 Groundworks and foundations: [included / by others]

- Excavation for foundation cassettes: [size and depth] to the manufacturer's details, matching the tested foundation where rated.
- Survey for buried services before excavation: [included / by others].
- Drainage: each cassette connected to [surface water drain / soakaway] with [size] mm pipe; [silt trap / rodding access] [required / not required].
- Concrete: [grade] to the manufacturer's details.
- Ducts, draw pits and surface reinstatement: [included / by others].
- Where by others: provide drawings by [date / stage] and inspect before concreting.

5.9 Finishes

- Bollard sleeve: [polyester powder coat / stainless steel: grade and finish], colour [RAL or BS colour], with [reflective banding].
- Top cover / collar: [finish].

5.10 Testing and commissioning

As clause 1.10, including tests of presence detection, traffic lights, emergency operation and manual lowering. Where impact rated, confirm in writing that the installation matches the tested foundation and arrangement.

5.11 Documentation and handover

As clause 1.11. Where impact rated, include the test certificate or rating evidence and the manufacturer's confirmation that the installation matches the test. See clause 11.

5.12 Training

As clause 1.12, including manual lowering and emergency operation.

5.13 Warranty

Parts: [term]. Labour: [term]. Conditions: [conditions, e.g. excludes vehicle impact damage and drainage failures not caused by the Contractor].

5.14 Maintenance

As clause 1.14, including drainage checks at each planned visit.

5.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and model], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and model] or equivalent. Any equivalent must meet every requirement in this clause, including any impact rating. Evidence of equivalence, including test certificates, to be provided with the tender.

Road blocker

Draft: to be checked by UrbanForte before use.

Uniclass system
Ss_25_36_95_40 Hydraulic ramp systems (use only where a hydraulic ramp describes the blocker)
Uniclass product
Not shown.
CAWS work section
Not shown.
NRM1
8.4.4 Barriers and guardrails (mapping from the NBS Uniclass Systems table v1.44; not checked against the RICS publication); hydraulic ramp systems only.
NRM2
Project QS to confirm.
CPV, supply
35121000-8 Security equipment (broad security-equipment classification); 34928110-2 Road barriers (conditional alternative where this accurately describes the purchase; within the crash-barriers branch)
CPV, installation
51100000-3 Installation services of electrical and mechanical equipment (for a separately procured equipment-installation service); 45233280-5 Erection of road-barriers (only where the work genuinely matches road-barrier works)
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment)
Short clause
Supply, install, test and commission [number] road blocker(s) at [location], complete with drives, controls, safety devices, drainage, signage and accessories. Type: [surface-mounted / shallow-mount / deep-mount], [hydraulic / electromechanical]. Control the risks of the plate rising beneath a vehicle or person and crushing at its hinge line and sides. Where impact rated, the installed foundation must match the tested foundation. Test presence detection, traffic lights, emergency operation and manual lowering as clause 5.10. Provide rating evidence where relevant, the clause 11 handover pack and the training required by clause 5.12.
Full clause
6.1 Scope

Supply, install, test and commission [number] road blocker(s) at [location], complete with blocker units, drive units, controls, safety devices, drainage connections, signage and all accessories needed for a safe, working installation.

6.2 Description

- Type: [surface-mounted / shallow-mount / deep-mount], [hydraulic / electromechanical].
- Width: [width] m. Height when raised: [height] mm.
- Plate: [material, finish], with [anti-slip surface] and [reflective / high-visibility markings].
- Manual lowering for power failure: [type], operable by persons permitted by the client only.

6.3 Performance requirements

- Rise time: [time] seconds. Lower time: [time] seconds.
- Operating cycles: rated for at least [number] cycles per [period].
- Impact rating: [not required / required: rating], tested to [BS ISO 22343-1:2023 / PAS 68 (legacy test, product accepted) / IWA 14-1 (legacy test, product accepted)]. Installed foundation to match the tested foundation.
- Load when lowered: [load class or axle load].
- Operating temperature range: [range] °C. Ingress protection: [IP rating].
- Power failure behaviour: [stay up / lower / stay in last position], with [battery back-up / emergency lowering].
- Emergency fast operation: [required / not required].

6.4 Standards and legislation

As clause 5.4. PAS 170-1 does not cover blockers.

6.5 Safety devices and force testing

As clause 5.5. In addition: control the risk of the blocker plate rising under a vehicle or person, and the risk of crushing at the hinge line and sides of the plate.

6.6 Controls and integration

As clause 5.6.

6.7 Electrical (BS 7671)

As clause 5.7.

6.8 Groundworks and foundations: [included / by others]

As clause 5.8, for a [surface-mounted / shallow / deep] foundation of [size and depth], matching the tested foundation where rated.

6.9 Finishes

- Plate and frame: [finish], colour [colour], with [markings].

6.10 Testing and commissioning

As clause 5.10.

6.11 Documentation and handover

As clause 5.11. See clause 11.

6.12 Training

As clause 5.12.

6.13 Warranty

As clause 5.13: parts [term], labour [term], conditions [conditions].

6.14 Maintenance

As clause 5.14.

6.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and model], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and model] or equivalent. Any equivalent must meet every requirement in this clause, including any impact rating. Evidence of equivalence, including test certificates, to be provided with the tender.

Access control

Draft: to be checked by UrbanForte before use.

Uniclass system
Ss_75_40_02_11 Credential access control systems (for credential-based systems)
Uniclass product
Not shown.
CAWS work section
Not shown: not verified.
NRM1
5.12.2 Security systems (mapping from the NBS Uniclass Systems table v1.44; not checked against the RICS publication)
NRM2
Project QS to confirm.
CPV, supply
42961100-1 Access control system
CPV, installation
45310000-3 Electrical installation work (for an installation works package)
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment)
Short clause
Supply, install, configure, test and commission an access control system for [list of gates, barriers, bollards, doors] at [location], including controllers, readers, credentials, power supplies, software, network connections and cabling. Number of users: [number]. Keep controllers operating and logging during network or server failure. Interfaces must never bypass powered-equipment safety devices. Test every reader, credential type, access level, time zone, interface and alarm, including off-line and power-failure behaviour. Provide configuration backups, drawings, user guidance and records under clause 11, with passwords handed over securely and separately. Train [number] administrators and [number] day-to-day users.
Full clause
7.1 Scope

Supply, install, configure, test and commission an access control system for [list of gates, barriers, bollards, doors] at [location], complete with controllers, readers, credentials, power supplies, software, network connections and all cabling and accessories.

7.2 Description

- System: [system, e.g. Paxton Net2: specify version / other]. The named brand is for example only, as a preferred brand chosen from experience.
- Controllers: [number], located at [location].
- Readers: [number and type, e.g. proximity / keypad / Bluetooth / long-range / ANPR], at [locations], mounted at [height] mm on [posts / goosenecks / walls].
- Credentials: [tokens / cards / key fobs / mobile credentials / ANPR number plates / PIN], quantity [number].
- Visitor management: [required: details / not required].
- Software: [server / PC / cloud], hosted on [client equipment / Contractor-supplied PC / cloud service], with [number] administrator licences.

7.3 Performance requirements

- Number of users the system must support: [number]. Number of doors / entry points: [number], with capacity to expand to [number].
- Read range (long-range or ANPR): [range] m.
- Event log: store at least [number] events or [period], whichever is greater.
- Access levels and time zones: [requirements].
- Anti-passback: [required / not required].
- Network: [stand-alone / client LAN / separate VLAN], with [encryption] and [password policy].
- Off-line operation: controllers to keep working and logging if the PC, server or network fails.
- Power failure: [battery back-up for period / none]. Door / gate behaviour on power failure as set by the equipment clauses and the fire strategy.

7.4 Standards and legislation

Comply with the current editions of the following, as relevant:

- BS EN 60839-11-1 Alarm and electronic security systems. Electronic access control systems. System and components requirements [specifier to state grade if needed].
- BS 7671 and the Electricity at Work Regulations 1989.
- UK GDPR and the Data Protection Act 2018 for personal data, including ANPR number plate data and event logs. The client is the data controller. The Contractor must set up the system so the client can meet their duties (retention periods, access to data, security).
- Building Regulations fire safety guidance (Document B, current edition, for England) and the fire strategy, for any doors or gates on escape routes; use the relevant national guidance elsewhere.
- Manufacturer's instructions.

7.5 Safety devices and force testing

- Access control may only give an open command. It must never bypass or override the safety devices of powered gates, barriers, bollards or blockers.
- Where access control is added to existing powered equipment, the equipment must be reassessed and, where needed, retested to the equipment clause (clauses 1, 2, 3, 5, 6). Record the outcome.
- Fail-safe / fail-secure locking: [details for each door or gate], agreed with the client and fire strategy.

7.6 Controls and integration

- Integration with: [gate / barrier / bollard / blocker controllers], [GSM intercom: see clause 8], [fire alarm], [CCTV], [intruder alarm], [lift control], [car park management], [other].
- ANPR, for example: [Paxton ANPR / other], cameras at [locations], with [whitelist management by client].
- Free exit: [method].
- Remote management: [required / not required], by [app / web], with [security arrangements].

7.7 Electrical (BS 7671)

- Mains supply for controllers and power supplies: [by Contractor / by others], with local isolation.
- Low-voltage and data cabling: [cable types], in [containment], segregated from mains.
- External cabling in ducts; external equipment rated [IP rating].
- Electrical certificate to BS 7671 for any mains work.

7.8 Groundworks and foundations: [included / by others]

Reader posts, gooseneck foundations, ducts and draw pits: [included / by others], to [details].

7.9 Finishes

Reader posts and housings: [finish], colour [colour]. Labels identifying each reader and controller with the asset reference.

7.10 Testing and commissioning

- Test every reader, credential type, access level, time zone, interface and alarm.
- Test off-line operation and power-failure behaviour.
- Test that access control inputs cannot override safety devices on powered equipment.
- Set up users and credentials: [Contractor to load data provided by client / client to load].
- Record results.

7.11 Documentation and handover

Provide: system schematic, as-installed drawings showing reader and controller positions, cable schedule, configuration backup, software licence details, administrator user names (passwords handed over securely and separately), user guide, test records and asset references. See clause 11.

7.12 Training

Train [number] administrators in adding and removing users, issuing credentials, access levels, reports and backups. Train [number] day-to-day users. Record attendance.

7.13 Warranty

Hardware: [term]. Labour: [term]. Software support and updates: [term / not included]. Conditions: [conditions].

7.14 Maintenance

[Included for term / quoted separately]: planned checks of readers, controllers, batteries and backups, and software updates. See clauses 9 and 10.

7.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and system, e.g. Paxton Net2], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and system] or equivalent. Any equivalent must meet every requirement in this clause. Evidence of equivalence to be provided with the tender.

GSM intercom

Draft: to be checked by UrbanForte before use.

Uniclass system
Ss_75_40_02_05 Audio intercom systems; Ss_75_40_02_94 Video intercom systems. Select by audio/video function; GSM is described in the clause, not coded.
Uniclass product
Not shown.
CAWS work section
Not shown.
NRM1
5.12.1 Communication systems (mapping from the NBS Uniclass Systems table v1.44; not checked against the RICS publication); audio intercom only.
NRM2
Project QS to confirm.
CPV, supply
32360000-4 Intercom equipment (describe GSM and audio/video characteristics in the clause)
CPV, installation
45314000-1 Installation of telecommunications equipment (for works); 51300000-5 Installation services of communications equipment (for a separately procured equipment-installation service)
CPV, maintenance
50330000-7 Maintenance services of telecommunications equipment; 50610000-4 Repair and maintenance services of security equipment (where procured as integrated security-entry equipment)
Short clause
Supply, install, configure, test and commission [audio / video] GSM intercom(s) at [location], to call [mobile numbers / app / landline] and open [gate / barrier / door] on command. Check and record mobile signal strength before installation. The intercom must never bypass equipment safety devices, and remote opening must be permitted by the equipment risk assessment. Test calls, dial-to-open, relay outputs, equipment interfaces, video where fitted and signal strength. Provide wiring, programming and SIM records, user guidance and asset references under clause 11. Train [number] client nominees and record attendance.
Full clause
8.1 Scope

Supply, install, configure, test and commission [audio / video] GSM intercom(s) at [location], to call [mobile numbers / app / landline] and open [gate / barrier / door] on command.

8.2 Description

- Call points: [number], with [single / multiple] call buttons and [keypad / proximity reader / none].
- Mounting: [post / wall / gooseneck] at [height] mm for [car drivers / pedestrians / both]. Provide a second call point at [height] mm for [high vehicles / pedestrians] where required.
- Video: [camera type / not required].
- Answering: [number] numbers in call order [details], or [app].
- Housing: [material], [vandal-resistant].

8.3 Performance requirements

- Mobile network: [network technology, e.g. 4G] capable, with [dual SIM / single SIM]. Signal strength at the call point to be checked before installation and recorded.
- Number of permitted caller-ID numbers for free entry (dial to open): [number].
- Relay outputs: [number], rated for the connected equipment.
- Call time limit: [time]. Door / gate open time: [time].
- Operating temperature range: [range] °C. Ingress protection: [IP rating].
- Accessibility: [induction loop / visual call indicators / other] where required.

8.4 Standards and legislation

- Radio Equipment Regulations 2017 (as amended): UKCA or CE marking of the intercom under the applicable Great Britain route; CE marking for Northern Ireland, with UKNI where required by the conformity-assessment route.
- BS 7671 and the Electricity at Work Regulations 1989.
- UK GDPR and the Data Protection Act 2018 where video or call logs record personal data.
- Equality Act 2010 for accessible call points, where relevant.
- Manufacturer's instructions.

8.5 Safety devices and force testing

- The intercom may only give an open command. It must never bypass or override the safety devices of powered equipment.
- Remote opening by a person who cannot see the gate or barrier is only acceptable where the equipment's risk assessment allows it. Where an intercom is added to existing powered equipment, reassess and retest the equipment as clause 7.5.

8.6 Controls and integration

- Opens: [equipment], by [relay / input to access control].
- Integration with access control (clause 7): [required / not required].
- Remote programming: [SMS / app / PC software], with PIN protection.

8.7 Electrical (BS 7671)

As clause 7.7. Antenna: [integral / external], position [location].

8.8 Groundworks and foundations: [included / by others]

Posts, ducts and draw pits: [included / by others].

8.9 Finishes

Housing: [finish], colour [colour]. Post: [finish], colour [colour]. Instruction label at the call point.

8.10 Testing and commissioning

Test calls to every number, dial-to-open, relay outputs, interface with each item of equipment, video (if fitted) and signal strength. Record results.

8.11 Documentation and handover

Provide: wiring diagram, programming record (numbers, settings), SIM details and airtime account holder, user guide, test record and asset references. See clause 11.

8.12 Training

Train [number] client nominees in answering, opening, adding and removing numbers. Record attendance.

8.13 Warranty

Hardware: [term]. Labour: [term]. Conditions: [conditions].

8.14 Maintenance

SIM and airtime: supplied and paid for by [client / Contractor: term and charges]. Maintenance: [included / quoted separately]. See clauses 9 and 10.

8.15 Product

Product: use ending A or ending B below.
Product endings: named, or equivalent
Ending A (named product): Product: [manufacturer and model, e.g. Videx model], as preferred by the client.
Ending B (or equivalent): Product: [manufacturer and model] or equivalent. Any equivalent must meet every requirement in this clause. Evidence of equivalence to be provided with the tender.

Planned maintenance

Draft: to be checked by UrbanForte before use.

Uniclass activity
Ac_85 Operation and maintenance activities; Ac_85_10_06 Barrier maintenance (for barrier work; planned is a service attribute)
Uniclass information
PM_80_10_52 Maintenance plan information (for the maintenance plan document)
CAWS work section
Not shown.
NRM1
Not shown.
NRM2
Project QS to confirm.
CPV, supply
Not shown: separately purchased replacement goods use their relevant product codes.
CPV, installation
Not shown: select only if installation or replacement work forms part of the procurement.
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment); 50330000-7 Maintenance services of telecommunications equipment (for telecoms maintenance); 50710000-5 Repair and maintenance services of electrical and mechanical building installations (for a wider building-installations maintenance contract)
Short clause
Provide planned maintenance of [list of equipment, with asset references] at [site(s)] for [term], starting [date]. Visits: [number] per year per item, at intervals of [interval]. Inspect structure, fixings and moving parts; test safety devices, manual release, controls and interfaces; clean, lubricate and adjust to the manufacturer's instructions. Force testing: [every visit / interval], with results recorded. Check drainage for bollards and blockers. Make safety-critical defects safe immediately and tell the client the same day. Issue a written report within [time], maintain each asset log and hand over the full log at the end of the term.
Full clause
9.1 Scope

Provide planned maintenance of [list of equipment, with asset references] at [site(s)] for a contract period of [term], starting [date].

9.2 Description

- Visits: [number] per year per item, at intervals of [interval], scheduled with the client to suit the estate's working pattern.
- Equipment covered: as the asset list in [appendix]. Equipment added during the term to be added by [agreed variation].
- Working hours: [hours]. Visits outside these hours: [by agreement / at rates in schedule].

9.3 Performance requirements

Each visit must include, for each item:

- Visual inspection of structure, fixings, foundations, hinges, tracks, rollers, stops and guards.
- Check and test of every safety device, including photocells, safety edges, loops and warning lights.
- Force testing to BS EN 12453 and DHF TS 013-1:2025 at [every visit / interval], using a calibrated instrument, with results recorded.
- Check of manual release and power-failure operation.
- Check of controls, access control and intercom interfaces.
- Cleaning, lubrication and adjustment to the manufacturer's instructions.
- Battery checks and replacement at [interval / condition].
- For bollards and blockers: drainage check and clearing of cassettes.
- Review of whether the risk assessment is still valid (changes in site use, layout or users).
- Safety-critical defects: make the equipment safe immediately (for example, put it out of service), tell the client the same day, and confirm in writing.

9.4 Standards and legislation

- DHF TS 013-1:2025 and, for owners, DHF TS 013-3 (guidance for owners and managers).
- BS EN 12453.
- Provision and Use of Work Equipment Regulations 1998, where the equipment is work equipment, and Workplace (Health, Safety and Welfare) Regulations 1992, where applicable. Maintenance duties fall on the relevant employer or person with control of the work equipment or workplace, according to the Regulations.
- Manufacturer's maintenance instructions.

9.5 Safety devices and force testing

See 9.3. Calibration certificates for force testing instruments to be available on request.

9.6 Controls and integration

Check that interfaces cannot override safety devices. Report any changes made by others since the last visit.

9.7 Electrical (BS 7671)

Visual checks of isolators, cables, enclosures and earthing at each visit. Periodic inspection and testing of the supply circuit to BS 7671: [included at interval / by others].

9.8 Groundworks and foundations

Not applicable, other than reporting any movement, settlement or damage.

9.9 Finishes

Report damage to finishes. Touch-up: [included / quoted separately].

9.10 Testing and commissioning

Record test results at every visit against the asset reference.

9.11 Documentation and handover

- Written report for each visit within [time] of the visit, listing each asset, work done, test results, defects and recommendations, with a clear safety status for each item.
- Keep a maintenance log for each asset and add each report to it. Hand over the full log at the end of the term.
- Remedial work: quoted separately unless agreed in advance.

9.12 Training

Refresher briefing for client staff: [included at interval / on request].

9.13 Warranty

Workmanship on maintenance tasks: [term]. Parts fitted: [term].

9.14 Maintenance

Inclusions: [labour / travel / consumables / parts up to value]. Exclusions: [e.g. vehicle impact damage, vandalism, misuse, work by others, upgrades].

Reactive maintenance

Draft: to be checked by UrbanForte before use.

Uniclass activity
Ac_85_10_06 Barrier maintenance (for barrier work); Ac_10_70_75 Repair (for repair activity; reactive is a service attribute)
Uniclass information
PM_80_10_54 Maintenance records (for resulting records)
CAWS work section
Not shown.
NRM1
Not shown.
NRM2
Project QS to confirm.
CPV, supply
Not shown: separately purchased replacement goods use their relevant product codes.
CPV, installation
Not shown: select only if installation or replacement work forms part of the procurement.
CPV, maintenance
50610000-4 Repair and maintenance services of security equipment (where the assets are security/access equipment); 50333200-0 Repair and maintenance services of radiotelephony apparatus (only for cellular/radiotelephony apparatus repairs); 50710000-5 Repair and maintenance services of electrical and mechanical building installations (for a wider building-installations maintenance contract)
Short clause
Provide reactive maintenance and breakdown repair for [list of equipment, with asset references] at [site(s)] for [term]. Reporting route: [phone / fault form / email / portal], available [hours]. On arrival, make the equipment safe before repair or temporary repair. After repairs affecting safety devices, drives, controls or moving parts, test all safety devices and carry out force testing where relevant before returning equipment to service. Record the fault, attendance times, work, parts, tests and safety status against the asset reference. Send records within [time] and provide [monthly / quarterly] performance reports. Repairs above [value] need client approval, except to make safe.
Full clause
10.1 Scope

Provide reactive maintenance and breakdown repair for [list of equipment, with asset references] at [site(s)] for a contract period of [term].

10.2 Description

- Reporting route: [phone / fault form / email / portal], available [hours].
- Fault categories, agreed with the client:
- Category [A: e.g. safety-critical or site cannot be secured]: attend within [response time].
- Category [B: e.g. equipment out of use]: attend within [response time].
- Category [C: e.g. minor fault]: attend within [response time].
- Out-of-hours cover: [included / not included / at rates in schedule].

10.3 Performance requirements

- Response time is measured from [the time the fault is logged] to [arrival on site].
- On arrival: make the equipment safe first, then repair or make a temporary repair.
- First-time fix target: [target]. Permanent repair within [time] where parts are needed.
- Spare parts: hold or have access to [critical spares list] to meet the response times.
- Equipment left in manual or out-of-service mode to be clearly signed and the client told.

10.4 Standards and legislation

As clause 9.4. After any repair to a safety-related part, retest to BS EN 12453 and DHF TS 013-1:2025 before returning the equipment to service. A repair that changes the way the equipment works, or its safety, may be a substantial modification under the Supply of Machinery (Safety) Regulations 2008: [Contractor to advise the client before carrying it out].

10.5 Safety devices and force testing

After any repair affecting safety devices, drive, controls or moving parts: test all safety devices and carry out force testing where relevant. Record results.

10.6 Controls and integration

Check that interfaces work and cannot override safety devices after any repair.

10.7 Electrical (BS 7671)

Electrical work to BS 7671, with certificates for any new circuits or alterations.

10.8 Groundworks and foundations

Not included unless quoted. Report any foundation damage.

10.9 Finishes

Not included unless quoted.

10.10 Testing and commissioning

As 10.5, before handing back the equipment.

10.11 Documentation and handover

Record each attendance against the asset reference: time logged, time arrived, fault found, work done, parts used, tests carried out and safety status on leaving. Send to the client within [time]. Provide [monthly / quarterly] performance reports against response times.

10.12 Training

Not applicable, unless the fault was caused by misuse: brief the client and recommend [training / signage].

10.13 Warranty

Repairs: workmanship [term], parts [term].

10.14 Maintenance

Charges: [included in contract / call-out and hourly rates in schedule / parts at cost plus agreed margin]. Repairs above [value] need client approval before work starts, except to make safe.

Handover pack

Draft: to be checked by UrbanForte before use.

Uniclass activity
Ac_05_60_35 Handing over (for the activity)
Uniclass information
PM_70_85 Completion information; PM_70_85_56 Operation and maintenance manual (where this is the deliverable)
Uniclass form
FI_90_50 Manual (MA) (for the information form)
CAWS work section
Not shown.
NRM1
Not shown.
NRM2
Project QS to confirm.
CPV, supply
Normally no standalone code: an ancillary contract deliverable. 22473000-6 Technical manuals (only for separately purchased technical manuals as goods)
CPV, installation
Not shown.
CPV, maintenance
Not shown.
Short clause
Provide a complete handover pack for each item of equipment, identified by its asset reference. Include the applicable declarations and marking evidence, risk assessment, commissioning and electrical records, drawings, settings, user and maintenance instructions, warranties, maintenance schedule and training records. The installer acting as manufacturer retains the technical file for the enforcing authorities. Format: [paper / PDF / both], [number] copies. Electronic files: [searchable PDF / native files], delivered by [method]. Deliver within [time] of practical completion. Update the pack after modifications and issue updated pages within [time].
Full clause
11.1 Scope

On completion of each installation, provide a handover pack for each item of equipment, identified by its asset reference.

11.2 Description

The pack must contain the following records, as applicable to the equipment, work carried out and conformity regime:

- Technical file summary and confirmation of where the full technical file is held, where machinery legislation applies. The installer acting as manufacturer compiles and retains the full technical file for the enforcing authorities; the full technical file is not part of the client handover pack.
- Declaration of conformity for the completed installation where required by the applicable legislation, and declarations for supplied components where relevant.
- Marking evidence under the applicable conformity regime, including UKCA or CE marking for Great Britain where required (photograph of the marking plate in position); use the applicable Northern Ireland marking where relevant.
- Site-specific risk assessment, with residual risks clearly stated.
- Commissioning records, including safety device tests and force test results with the instrument's calibration details.
- Electrical certificates to BS 7671.
- As-installed drawings: layout, foundations, ducts, cable routes, safety device positions and loop layouts.
- Wiring diagrams and control panel settings.
- User instructions and maintenance instructions in English, including manual release and emergency procedures.
- Product data sheets for main components.
- Impact rating evidence and foundation confirmation (bollards and blockers, where rated).
- Access control and intercom configuration records (passwords handed over separately and securely).
- Warranty details and the start date.
- Recommended maintenance schedule and spare parts list.
- Training attendance records.
- Asset list, with asset reference, location, product and serial number.
- Contact details for maintenance and fault reporting.

11.3 Performance requirements

The pack must be complete before handover. Handover may be refused if the pack is incomplete.

11.4 Standards and legislation

Supply of Machinery (Safety) Regulations 2008, as amended and where applicable; BS EN 12453; DHF TS 013-1:2025; BS 7671; Construction (Design and Management) Regulations 2015 (information for the health and safety file where more than one contractor is involved or reasonably foreseeable, whether or not the project is notifiable). Apply the relevant machinery regime described in clause 1.4.

11.5 to 11.10

Not applicable to this clause, other than as records of the tests and work in the product clauses.

11.11 Documentation and handover

- Format: [paper / PDF / both], [number] copies.
- Electronic files: [searchable PDF / native files], named with the asset reference, delivered by [method].
- Provide information for the health and safety file and O&M manual: [required / not required], in the format [format].
- Deliver within [time] of practical completion.

11.12 Training

Training records form part of the pack.

11.13 Warranty

Warranty certificates form part of the pack.

11.14 Maintenance

The pack must be updated after any modification. Updated pages to be issued within [time].

Common definitions

  • Contractor

    the party carrying out the work in the clause.

  • Employer / client

    the party for whom the work is done.

  • Equipment

    the powered or manual gate, barrier, bollard, blocker or system described in the clause, including its drive, controls, safety devices and accessories.

  • Asset reference

    a unique reference given to each item of equipment and recorded on the equipment, in the handover pack and in all maintenance records.

  • Risk assessment

    the site-specific assessment of hazards and controls for the equipment as installed, carried out in line with BS EN 12453 and DHF TS 013-1:2025 where applicable, and kept with the technical file.

Codes and dated legal and standards references checked on 29 November 2026 against the supplied code audit and opened primary sources; catalogue checks establish titles and status, not every technical requirement. Uniclass Systems and Products tables v1.44, October 2026. The standards, legislation and guidance documents themselves are the authority; check their scope, the project location and the edition in force before use. The source questions and the bollard and blocker force-testing wording remain for UrbanForte to resolve.